Complete Orange Line Metro Train project till May 20, SC directs construction companies

04:03 PM | 19 Apr, 2019
Complete Orange Line Metro Train project till May 20, SC directs construction companies
ISLAMABAD – The Supreme Court on Friday expressed annoyance over the delay in Orange Line Metro Train project and directed the construction companies to complete work by May 20.

A division bench of the apex court, comprising Justice Gulzar Ahmed and Justice Ijaz Ul Ahsan, heard the case.

During the course of proceedings, Justice Gulzar Ahmed also directed the all three construction companies to submit Rs 10 million guarantee each and remarked that the guarantee amount would be forfeited if the project is not finished by May 20.

He hoped this project would be successful and would not come crashing down.

Justice Gulzar expressed concern over current project director Fazal Haleem and observed due to him the work has been delayed.

He directed that Justice (Retd) Jamshed or Justice Abdul Sattar Asghar be made the head of the technical committee. He remarked that the Punjab government should consider if the current technical committee head Justice (retd) Zahid Hussain wanted to continue work.

He remarked that if the contractors do not work, fire them or put them in prison. The project director is apparently being blackmailed by the construction companies, he added.

https://en.dailypakistan.com.pk/headline/second-trial-run-of-orange-line-metro-train-today/

Justice Gulzar remarked that all three construction companies will give a guarantee of Rs1 billionand it will be confiscated if work is not completed by the scheduled date.

Advocate Naeem Bukhari, counsel for the construction companies, said that his clients could not give guarantee of Rs one billion. He said that his clients have already given Rs two billionguarantee.

He said that his clients' dues worth Rs 1.5 billion were pending.

Justice Ijaz Ul Ahsan remarked that it is a public interest project and huge funds have been used for metro train project.

Justice Gulzar asked if there is any mechanism to check the quality of construction of the project.

The Project Director said that their consultants were supervising the construction work of Orange Line Metro Train project.

The hearing was then adjourned for two weeks.

https://en.dailypakistan.com.pk/pakistan/sc-orders-lda-to-pay-rs1bn-to-orange-line-trains-construction-companies/

Daily Pakistan Global Web Desk

Advertisement

Currency Rates in Pakistan Today - Pakistani rupee to US Dollar, Euro, Pound, Dirham, and Riyal - 19 April 2024

Pakistani currency saw minor adjustment against global currencies on April 19, 2024. US dollar was being quoted at 277.4 for buying and 280.4 for selling.

Euro comes down to 293 for buying and 296 for selling while British Pound stands at 342.25 for buying, and 345.65 for selling.

UAE Dirham AED was at 75.2 and Saudi Riyal's new rates was at 73.30.

Today’s currency exchange rates in Pakistan - 19 April 2024

Currency Symbol Buying Selling
US Dollar ‎USD 277.4 280.4
Euro EUR 293 296
UK Pound Sterling GBP 342.25 345.65
U.A.E Dirham AED 75.2 75.9
Saudi Riyal SAR 73.3 74.05
Australian Dollar AUD 181 182.8
Bahrain Dinar BHD 740.09 748.09
Canadian Dollar CAD 201 203
China Yuan CNY 38.44 38.84
Danish Krone DKK 39.69 40.09
Hong Kong Dollar HKD 35.53 35.88
Indian Rupee INR 3.33 3.44
Japanese Yen JPY 1.86 1.94
Kuwaiti Dinar KWD 902.64 911.64
Malaysian Ringgit MYR 58.08 58.68
New Zealand Dollar NZD 164.22 166.22
Norwegians Krone NOK 25.31 25.61
Omani Riyal OMR 722.87 730.87
Qatari Riyal ‎QAR 76.45 77.15
Singapore Dollar SGD 204.5 206.5
Swedish Korona SEK 25.31 25.61
Swiss Franc CHF 305.08 307.58
Thai Bhat THB 7.56 7.71

Advertisement

Follow us on Facebook

Follow us on Twitter

Sign up for Newsletter